2.5 Powering on the Device
This section provides the checklist used to check the S2700/3700/5700/6700 switches before
and after powering on the switches.
Checklist before power-on
CAUTION
Do not frequently power on and off a switch.
No. Item Method
1 The chassis is installed in a position that meets the
requirements specified in the engineering design
document.
View
2 There are no fingerprints, stains, or scratches on the
surface of the chassis.
View
3 Mechanical parts of the cabinet are correctly installed in
the cabinet and comply with the installation standards. No
parts are loosened or damaged.
View
4 All the screws are fastened. View
5 No objects are placed on the chassis. View
6 There is at least 50 mm clearance between the cabinet and
both sides of the chassis for heat dissipation.
Measure
7 The signal cables are not damaged or broken and have no
splice.
View
8 The connectors of signal cables are clean and intact and
are connected to interfaces safely. Wires of cables are
fixed.
View
9 Both ends of signal cables are clearly labeled and the label
text is in the same direction.
View
S2700&S3700&S5700&S6700 Series Ethernet Switches
Quick Start Guide 2 Device Installation
Issue 12 (2013-07-25) Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
30