18
1. Log in to the FusionSolar app and choose My > Device
commissioning. The Device commissioning screen (Refer to
7.1 Device Commissioning.) is displayed.
2. Choose Power adjustment > Battery control and set battery
parameters, including Charge from grid, Control mode (Fixed
charge/discharge, Maximum self-consumption, Time-of-
use), Forced charge/discharge, and so on.
If the solar inverter connects to batteries, set battery parameters.
a. Log in to the FusionSolar app. On the Device commissioning screen, choose
Maintenance > Physical layout design of PV modules. The Physical layout design of
PV modules screen is displayed.
b. Tap the blank area. The Identify image and Add PV modules buttons are displayed. You
can use either of the following methods to perform operations as prompted:
• Method 1: Tap Identify image and upload the physical layout template photo to complete
the optimizer layout. (The optimizers that fail to be identified need to be manually bound.)
• Method 2: Tap Add PV modules to manually add PV modules and bind the optimizers to
the PV modules.
1. If the solar inverter is not connected to the FusionSolar Smart PV Management System,
access the Device commissioning screen (Refer to 7.1 Device Commissioning.) on the
FusionSolar app to set the physical layout of Smart PV Optimizers.
Setting Battery Parameters
6.5
Scenario 2: Setting on the Solar Inverter Side (Solar Inverter Not Connected to the
Management System)