Figure 5-20 Removing the top cover from the connection box
Step 3 Install the lower shell of the PG box.
Figure 5-21 Installing the lower shell of the PG box
Step 4 Route the cable through the gland.
Figure 5-22 Routing the cable through the gland
Step 5 Install AC output power cables and then AC input power cables in sequence.
Single-phase input single-phase output
a. Take out a short-circuit copper bar from the tting bag and short-circuit
L1, L2, and L3 using the short-circuit copper bar.
b. Secure the AC power cables to the wiring ports.
UPS2000-H-(6 kVA-10 kVA)
User Manual 5 Installation and Cable Connection
Issue 03 (2023-08-20) Copyright © Huawei Digital Power Technologies Co., Ltd. 69