2 - 2 Operation Requirements 704-0212-209 VM Series Maintenance and Safety Manual
Machine Installation
Inspect the machine to ensure that all parts are included and intact. The owner is
responsible for proper site preparation before the machine is installed. A Hurco Field
Service Engineer must install the machine in the prepared location. This location must
not subject the machine to uncontrolled cabinet temperatures or unfavorable work
environment conditions that could cause electronic component failure.
If the owner decides later to move the machine from its installed location, it is
recommended that the owner call Hurco for assistance.
Guarding System
Each machine has a self-contained guarding system. Inspect the machine to ensure the
guarding system is intact.
The chip doors, or enclosure doors, on the front of the machine lock during
Automatic Run Mode to prevent access to the moving parts of the machine.
The guards on each side of the machine are either movable or fixed. The
movable guards can be opened to access the inside of the machine. A special
key is required to open a fixed guard.
Foundation Conditions
The foundation must be able to support the weight of the machine, and should be
constructed of continuous concrete (reinforced concrete is best). The thickness and
consistency of the concrete must be compatible with industry standards for supporting
machine weight. Actual requirements will depend upon the physical properties of
underlying soil. Friction pads or machine anchors may be required to assure optimal
machine performance.
Improper moving of the machine may result in personal injury or
damage to the machine.