INSTALLATION
DC SERIES COMBI BOILERS DC 23-84, DC 29-106, DC 33-124, DC 33-160
For the inlet air – Schedule 40 PVC, CPVC, ABS or PPs piping of any type is
permitted. Use same diameter as Vent pipe.
Combustion air piping is inserted directly into the 3" female stainless steel
tting on the top, right side of the boiler and run horizontally or vertically to the
outdoors. Bird screen of 1/4" stainless steel or plastic mesh eg. (IPEX System
636 drain grate for CPVC systems) is useful to guard against foreign objects.
Care must be taken to ensure adequate separation is maintained between the
air intake inlet and the vent terminal. Refer to the vent terminal conguration
drawings in the Vent Termination section above.
Support should be provided for intake piping, particularly so for horizontal runs
(follow local code).
1.4.8 “Indoor Air” Combustion Air Intake
Using Indoor Combustion Air is not approved for use with the DC series boilers.
1.4.10 Closet Installations
For installations in a conned space (such as a closet), ventilation openings may
be needed through a door or wall to prevent excessive heat from building up
inside the space.
The boiler shall not be exposed to ambient conditions above 122°F (50°C) or
below 32°F (0°C).

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the IBC DC 23-84 and is the answer not in the manual?

IBC DC 23-84 Specifications

General IconGeneral
BrandIBC
ModelDC 23-84
CategoryBoiler
LanguageEnglish

Related product manuals