installation and
servicing
Classic
Your Ideal installation and servicing guide
See reverse for
Classic users guide
SE9 FF, SE12 FF, SE15 FF, SE18 FF,
SE21 FF, SE24 FF & SE30 FF
When replacing any part on this appliance use only spare parts that you can be
assured conform to the safety and performance specification that we require. Do not
use reconditioned or copy parts that have not been clearly authorised by Ideal Boilers.
For the very latest copy of literature for specification purposes please visit our website
www.idealboilers.com where you will be able to download the relevant information in pdf format.
For details of document amendments, refer to page 3
January 2008 UIN 200 544 A05
200544-5.pmd 20/02/2008, 13:261
Question and Answer IconNeed help?

Do you have a question about the IDEAL Classic SE18 FF and is the answer not in the manual?

IDEAL Classic SE18 FF Specifications

General IconGeneral
Warranty2 Years
MountingWall Mounted
Fuel TypeNatural Gas
Max. Output (kW)18 kW
Output18kW

Summary

Benchmark Commissioning Checklist

Boiler

Section for boiler details within the commissioning checklist.

Controls

Section for controls checks in the commissioning checklist.

For the central heating mode

Section for central heating mode measurements and records.

Introduction

Current Gas Safety Regulations

Details on current gas safety regulations for installation.

Location of Boiler

Compartment Installations

Gas Supply

Requirements and considerations for the gas supply installation.

Flue Installation

Guidelines and recommendations for flue installation.

Electrical Supply

Sealed System Requirements

Safety Valve

Specifications and requirements for the safety valve.

Expansion Vessel

Details on the type, capacity, and charge pressure of the expansion vessel.

Sealed System Requirements - continued

Packaging and Casing Removal

Flue Assembly - Exploded View

Cutting the Flue - wall thicknesses of 114 to 600 mm

Mounting the Boiler

Flue Assembly - Exploded view

Fitting the Side Outlet Plates

Gas Connection

Electrical Connections

Requirements and procedures for electrical connections.

Pictorial Wiring

Two Spring Closed Valve Pumped only

Frost Protection

Guidance on installing and wiring frost protection thermostats.

Commissioning and Testing

Electrical Installation

Checks for electrical safety and preliminary system checks.

Gas Installation

Procedures for gas installation inspection, purging, and soundness testing.

Initial Lighting

Step-by-step guide for the initial lighting of the boiler.

Initial Lighting - continued

General Checks

Checks to ensure correct operation after installation.

Handing Over

Actions required for handing over the appliance to the householder.

Schedule

Cleaning the Fan Assembly; The Flueways

Cleaning the Burner and Pilot Assembly

Instructions for cleaning the burner and pilot assembly.

Gas Pressure Adjustment

Replacement of Parts

General procedure for replacing any component.

Thermostat Control, Thermistor Sensor Lead & On;Off Switch Replacement

Limit Thermostat Replacement

Ignition Electrode and Lead Replacement

Main Burner and Main Burner Injector Replacement

Procedure for replacing the main burner and its injector.

Gas Control Valve Replacement

Steps for replacing the gas control valve assembly.

Fan Replacement

Printed Circuit Board (PCB) Replacement

Instructions for replacing the printed circuit board.

Short List of Parts

Installer Notification Guidelines

Gas Boiler Commissioning Checklist

Controls To comply with the Building Regulations

Checks for controls compliance with building regulations.

For all boilers

Confirmation points applicable to all boiler types.