 | Acceptance and commissioning
56
YLS-K
6 Acceptance and commissioning
The commissioning of the product takes place in cooperation with the
service personnel of IPG Laser GmbH.
NOTICE
Damage to product components
The commissioning of the product may not take
place until all acceptance tests have been fully com-
pleted.
ð Perform all acceptance tests together with the
competent IPG service department in accor-
dance with the commissioning report.
6.1 Visual inspection
The visual inspection offers an initial overview of the condition of the
installation.
ð Ensure the following:
The space room conditions must be taken into account.
A space of 1 m must be maintained on all sides of the product.
The casters of the product must be locked (if present).
All plug connectors must be locked or screwed onto the product.
The product cabinet and the fiber must not exhibit any visible
damage.
6.2 Work to be performed before
commissioning
WARNING
Danger from laser radiation
Laser radiation can damage the eyes and skin.
ð Only perform the commissioning work in coop-
eration with the competent IPG service depart-
ment.