Chapter - Servicing Procedures5:6
CN101 - Maintenance
Adjustment of Steering Components - Tools required
1 x Trolley jack (capable of safely lifting the vehicle to the required height).
2 x Axle stands (sufcient to support the vehicle safely at the required height)
1 x 22mm open ended spanner.
2 x 17mm spanner.
1 x 19mm socket.
1 x 17mm socket
1 x torque wrench (Suitable for above sockets and able to give 40Nm and 100Nm measurements).
1 x Paint pen.
Parts required
Split pin 2mm x 30mm - as required.
Standard Repair Time
Adjustment of lock stops, steering and initial periodic inspection - 60 Minutes.
Periodic inspection - 15 Minutes.