TP-6803 6/15 19Section 1 Installation
10. Connect and turn on the new fuel supply.
11. Reconnect the generator set engine starting
battery leads, negative (--) lead last.
12. Reconnect the utility power to the generator.
13. Start the generator set by pressing the RUN button
on the generator set controller.
14. Check for leaks u sing a gas leak detector.
15. Run the generator set and check the operation.
16. Press the OFF button to shut down the generator
set.
Conversion from LPG to Natural Gas
To convert from LPG to natural gas, r epeat the steps
above, removing the LPG fuel orifice and installing the
NG fitting. Connect ignition timing leads 65 and N3
together for natural gas.
2
GM84143
1. Orifice fitting (see detail)
2. Hose barb fitting
ORIFICE FITTING DETAIL
1
Figure 1-12 14RESA/RESAL Fuel System Showing Orifice Fittings (generators built after June 26, 2014)

Other manuals for Kohler 20RESCL

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Kohler 20RESCL and is the answer not in the manual?

Kohler 20RESCL Specifications

General IconGeneral
BrandKohler
Model20RESCL
CategoryPortable Generator
LanguageEnglish

Related product manuals