Spreading operation B
154
AXIS 30.1 (W), AXIS 40.1 (W)
B.6 Calibration test
For precise control of the discharge amount we recommend running a new cali-
bration test every time you change fertiliser types.
Run the calibration test:
Before spreading for the first time.
If the fertiliser quality has changed greatly (moisture, high dust content,
cracked grain).
If a new fertiliser type is used.
The calibration test must be conducted (with engaged PTO shaft) at a standstill
or during travel over a test section.
NOTICE
The solid fertiliser broadcaster AXIS 50.1 Q is tested for calibration using the
electronic control system.
The calibration test is described in a separate operator's manual for the elec-
tronic control system. This operator's manual is part of the electronic control
system.
NOTICE
The solid fertiliser broadcaster AXIS 50.1 W is equipped with an electronic drop
point adjustment.
The drop point is automatically moved to the calibration position by the electron-
ic control system.