6-51
Machine transportation after setup > Procedure for the main unit transportation (Truck transportation)
[CONFIDENTIAL]
66
(Display: Manu0304) Make sure to check all the couplings [A] are connected and the
clamps [B] are closed again.
• Confirm if the ink is flowing into the tube of the supply side.
• Select [Execute] and press [Start] to continue.
67
(Display: Auto 0305) Run Simple Ink Inst.
• Run purge and remove air bubble in the supply side.
• Select [Execute] and press [Start] to run job.
• If error code is displayed, check the list and perform necessary action. (See page 5-15
)
Then select [execute] and press [start] to return step 69.
68
(Display: Finish) Complete ink installation
69
Exit from maintenance mode
70
Turn the power switch [A] off where is located at the front side of the main unit.