Page A - 78
A
LW 225 E / LW 245 B
Version: 19.11.2015
S T O R A G E
Note
Please check the specific handbook of the petrol engine regarding conservation / storage,
de-conservation and commissioning of the LW 100 B compressors.
i
De-conservation, commissioning
After the compressor has been stored, the following steps are to be taken:
If compressor hasn’t been used for longer than 12 months, we strongly recommend an oil
change before any use.
Replace intake filter cartridge and check oil level.
Clean compressor unit, check for foreign objects.
Check condition and tension of V-belts, replace if necessary.
Check condition of filling hoses, replace if necessary.
Secure hoses against whipping and open filling valves and run compressor for approximately
10 minutes.
Check condition of final filter cartridge, replace if necessary.
Close filling valves and run compressor up to final pressure.
Check safety valve relief pressure of final stage and/or pressure switch setting.
Check all connections and pipe work for leaks.
Once all above steps are completed, compressor unit is now ready for use.