Commissioning
5-1
SHB9300CRV EN 2.0
5 Commissioning
5.1 Before switching on
Prior to initial switch-onof the controller, check thewiring for completeness, short-circuit, and earth
fault:
l
Power connection:
– Supply via terminals L1, L2 and L3 (direct mains connection) or alternatively via terminals
+UG, -UG (DC bus connection, network of drives).
l
Motor connection:
– In-phase connection to the motor (direction of rotation).
l
Feedback system (resolver, incremental encoder, ¡).
l
Control terminals:
– Controller enable: Terminal X5/28 (reference potential: X5/39).
l
Covering the power connections:
– Put on cover(s) and fix.
l
Keep to the switch-on sequence! (
&
5-1)
l
The commissioning steps described in chapter 5 refer to the configuration C0005 = 10000.
Plese change the factory setting to this configuration!
Note!
The signal flow for configuration 1000 is described and shown in chapter ’Configuration’.
(See chapter 5.8,
(
&
5-12) ).
5.2 Initial switch-on
Note!
l
Use a PC with the Lenze program ”Global Drive Control” (GDC) under Windows for
commissioning. The convenient menus include the codes for the most important settings.
l
A communication module type 2102 ”RS232, RS485, optical fibre” (Lecom A/B) is required to
run the GDC. As alternative you can also use a system bus module (2173) as from GDC
version 3.0.
l
GDC and the communication module are not included in the delivery package of the
controller.
l
The “Electronic cam profiler” requires
GDC version 3.6 required.