Put the foot rail with the treadles in between
the front posts of the loom and connect these
parts with the four remaining screws.
Check the position the cords that connect the
lams to the lower shaft bars. The location on
the lams should be exactly in the middle.
Replace the connection to the lams if
necessary. Start with the ones in the front and
the back, so the ones in between can be
placed in line.
The hardware bag contains:
− 2 threaded ends 6 X 135 each with 2
washers and 2 wing nuts
− 4 screws 5 X 50
− 8 screws 4 X 15
− 2 ratchets
− 2 screws 4,5 X 17 (round head)
− 2 screw eyes 6
− 2 screws 3 X 20
− 2 beam handles with O-ring (If you are
going to have a brake on the warp beam,
you only need one)
− 3 O-rings (one is for spare)
− 60 tie-up cords for the treadles
− 6 beam cords
− 50 spare pegs to shorten cords