Massey Ferguson 6400 - Issue 4.a
2B11.12
Perkins/GTA2520 engine separation
Final steps
NOTE: Final steps are not especially difficult. They
should be carried out in the reverse order to
preliminary steps. However, it will be necessary during
reassembly to carry out the tightening torques,
checks, adjustments and tests described below.
Tightening torques
As required:
• front cab screws (see chapter 12)
• screw (2) of connector (1) on main wiring harness
(Fig. 6 and Fig. 12) 2.82 to 3.15 Nm
Topping-up
of coolant to the maximum level marked (radiator,
expansion tank Fig. 13).
Tests
- air conditioning system (if fitted—see chapter 12)
- cab suspension (if fitted—see chapter 12)
- all mechanical, hydraulic, electrical and electronic
functions subject to operations
Checking tightness
- of hydraulic unions
- of bleed screw on control unit of suspended front
axle (if fitted)
Fig. 12
Fig. 13