© Meunier Technologies Inc. 2021 - All rights reserved 22
Dosing Pump Calibration
DICE™ DS
1. The back pressure and pressure relief valve need
to be adjusted prior to pump calibration.
2. The evacuation (3) and injection valve (1) must be
in the closed position. The calibration column valve
(2) must be in the open position.
3. Once the pump calibration is done, open the
evacuation valve (3) to empty the calibration
column.
4. Close the evacuation (3) and calibration column
valve (2) and open the injection valve (1).
Refer to dosing system manual for the calibration procedure.
Note:
The top of the calibration column must be vented
in order to empty its contents using the
evacuation valve (3).
Refer to dosing pump manual for the calibration
procedure.