11. Test Operation
11.1  The test operation must be carried out 
after the entire installation has been  
completed.
11.2  Please confirm the following points 
before the test operation.
 • The indoor unit and outdoor unit are installed prop-
erly.
 • Tubing and wiring are correctly completed.
 • The refrigerant pipe system is leakage-checked.
 • The drainage is unimpeded.
 • The ground wiring is connected correctly.
 • The length of the tubing and the added stow capac-
ity of the refrigerant have been recorded.
 • The power voltage fits the rated voltage of the air 
conditioner.
 • There is no obstacle at the outlet and inlet of the 
outdoor and indoor units.
 • The gas-side and liquid-side stop values are both 
opened.
 • The air conditioner is pre-heated by turning on the 
power.
11.3  Test operation
1. Open both the liquid and gas stop valves. 
2. Turn on the main power switch and allow the unit to 
warm up. 
3. Set the air conditioner to COOL mode, and check the 
following points.
Indoor unit
 • Whether the switch on the remote controller works 
well.
 • Whether the buttons on the remote controller 
works well.
 • Whether the air flow louver moves normally.
 • Whether the room temperature is adjusted well.
 • Whether the indicator lights normally.
 • Whether the temporary buttons works well.
 • Whether the drainage is normal.
 • Whether there is vibration or abnormal noise during 
operation.
Outdoor unit
 • Whether there is vibration or abnormal noise during 
operation.
 • Whether the generated wind, noise, or condensed 
of by the air conditioner have influenced your neigh-
borhood.
 • Whether any of the refrigerant is leaked.
Drainage Test
a. Ensure the drainpipe flows smoothly. New buildings 
should perform this test before finishing the ceiling. 
b. Remove the test cover. Add 2000ml of water to the tank 
through the attached tube. 
c.Turn on the main power switch and run the air 
conditioner in COOL mode.  
d. Listen to the sound of the drain pump to see if it makes 
any unusual noises. 
e. Check to see that the water is discharged. It may 
take up to one minute before the unit begins to drain 
depending on the drainpipe. 
f. Make sure that there are no leaks in any of the piping. 
g. Stop the air conditioner. Turn off the main power switch 
and reinstall the test cover. 
If ambient temperature is below 17°C (63°F)
You can’t use the remote controller to turn on the COOL 
function when the ambient temperature is below 17°C. In 
this instance, you can use the MANUAL CONTROL button 
to test the COOL function.
1. Lift the front panel of the indoor unit, and raise it until it 
clicks in place.
2. The MANUAL CONTROL button is located on the right-
hand side of the display box. Press it two times to select 
the COOL function. 
3. Perform Test Run as normal.