1st Year 2 Year 3 Year 4 Year*
Condensate Neutralizer Check condensate neutralizer, making sure there is a sufficient quantity. Replenish if necessary.
Condensate System
Disconnect condensate piping, clean out dirt, fill with water to level of outlet and re-install. Remove
plug. Clean out, check for potential obstruction issues. (Note: You must verify the flow of condensate,
making sure that the cup is connected properly during final inspection.)
Pressure Measure incoming gas pressure (from 3.5" to 14" W.C.)
Pressure Drop Measure drop in pressure on light off (no more than 1" W.C.)
Check gas pipe for leaks Check piping for leaks, and verify they are all properly supported
Check CO/CO2 Levels
Check levels of CO and CO2 in Exhaust (See start up section 12 fig 12-1 for ranges) record at high and
low fire
ECO (Energy Cut Out) Check continuity on Flue and Water ECO, replace if corroded
Thermistors Check wiring, verify through ohms reading (see chart part 14 Fig. 14-3)
Check List
Verify that you have completed the entire check list WARNING: FAILURE TO DO SO COULD RESULT IN
DEATH OR SERIOUS INJURY.
Homeowner Review, with the homeowner what you have done
INIT
INIT INIT INIT
Tech Sign Off
DATE DATE DATE DATE
* NOTE : CONTINUE MAINTENANCE BEYOND THE 4TH YEAR IS REQUIRED ON A YEARLY BASIS.
Condensate
Gas
Combustion
Safeties
Date last completedInspection Activities
Final Inspection