3. Installation
3.1. Pre-Installation Requirements
Please note the following items related to this unit and its installation must be completed prior to scheduling the
factory technician for startup.
• All wiring (Power and Control), electrical components, control devices, and electrical service should
be completed in accordance with NFPA 70, NEC (National Fire Protection Association, National
Electrical Code). Wiring and components must also comply with all State and Local Code
requirements along with installation plans and unit specifications.
• All heating, venting, cooling, refrigeration, heat producing appliances, plumbing and piping should be
installed per UMC, ASHRAE (Uniform Mechanical Code, American Society Heating, Refrigeration
and Air Conditioning Engineers) requirements for building and energy efficiency. All components
must also comply with all State and Local Code requirements along with installation plans and unit
specifications.
• All air supply, ducting and connections must be completed per UMC, AMCA, and SMACNA
(Uniform Mechanical Code, Air Movement and Control Association - International Inc., Sheet Metal
and Air Conditioning Contractors National Association) specifications. All components must also
comply with all State and Local Code requirements along with installation plans and specifications.
3.2. Pre Checks and Inspection before Installation
The unit must be lifted by crane using all lifting points located on top of unit. The crane must be capable of
lifting weight shown on General Arrangement drawing. Failure to do so will damage the unit and void warranty.
See Figure 2 and Appendix D: General Arrangement for specific unit dimensions and weight.
For proper mounting, review all drawings; dimensions, ducting, submittal package, notes on orientation and
positioning and confirm this information before installing unit(s).
Figure 2: Lifting to prevent unit damage
Upon unit arrival, inspect immediately for signs of shipping damage. If you do notice any damage, report it to
the shipping company and to Munters immediately.
1. Check all items in the shipment carefully against the bill of lading. Be sure all of the listed items have been
received. Please check as some parts may have been shipped inside the unit.