Installation
18
NCR 4072 UPS Site Preparation, Installation, and Operation Manual S 05147374 Rev C Uncontrolled Copy
UPS Internal Battery Connection
Use the following procedure to ensure proper b attery operation before
installing the UPS:
1. Verify that the UPS is off and unplugged.
2. Remove the UPS front panel.
Figure 2. Removing the Front Panel
3. Slide up and remove the metal battery cover.
1400 VA500–1000 VA
Figure 3. Removing the Battery Cover