LIFT FROM THE STREET TO THE SET UP
LOCATION
If the base allows, the simplest thing is to use a pallet
truck to move the S2125 to the set up location.
The centre of gravity is offset to one side (see print on
the packaging).
If S2125 needs to be transported across soft ground,
such as a lawn, we recommend using a crane truck that
can lift it to the installation location. When S2125 is lifted
with a crane, the packaging must be untouched.
If a crane vehicle cannot be used the S2125 can be
transported on an extended sack truck. S2125 must be
taken from its heaviest side and two people are required
to lift S2125.
LIFT FROM THE PALLET TO FINAL
POSITIONING
Before lifting remove the packaging and the securing
strap to the pallet.
Place lifting straps around each machine foot. Lifting
from the pallet to the base requires four persons, one
for each lifting strap.
Supplied components
Local differences in the enclosed kit may occur. See
relevant installer manual for more information.
1 x automatic gas separat-
or
2 x flexible pipes (DN25,
G1") with 4 x gaskets
1 x non-return valve
8 NIBE S2125
IT'S IN OUR NATURE