24
10.2 CU-2TZ50TBE
10.2.1 Check Points
elevation:
10m max
.
elevation betwee
each of the indoo
units and betwee
the indoor and
outdoor units.
1.5mm
2
flexible cord x 4 core
(polychloroprene sheathed)
(Not included in the unit)
Outdoor unit power supply:
Single-phase 230V, 50Hz
16A switch
(circuit breaker)
(Not included in the unit)
1.5 mm
2
or more x 3 core
(Not included in the unit)
Drain work
Drain elbow
(Inner diameter: 16mm) provided
Outdoor wiring work
Unit B
Unit A
Applicable connecting tube kit:
CZ-3F type
Total maximum pipe length: 30m
Air purging: Air purging by vacuum pump.
UnitA Maximum pipe length: 20m
Unit B Maximum pipe length: 20 m
connection cables
(Not included in the unit)
Grounding work
10.2.2 The Shapes of the 3-Way Valve Caps of the Outdoor Unit Have Been Changed
Accompanying the changes in the shapes of the 3-way valve caps, the tightening method has also been changed.
Firmly tighten the 3-way valve caps by hand, and then tighten them up by another 30 degrees or so (one-twelfth
of a full turn) using a spanner or adjustable spanner.
Caution:
Approx. 30 degrees
Do not use all your strength to tighten up
the caps. Doing so may break the caps.
After having firmly tightened the caps by hand,
tighten them up further using a
spanner or adjustable spanner.