9
The correct operation of this equipment depends on the instructions in this manual.
To secure the equipment, proceed as follows:
1º Step: Make sure that the floor is firm enough so that the equipment can be
screwed so that it is level. If it does not comply with the requirement, provide a
concrete base, following the guidelines below:
2º Step: Base dimensions should be appropriate for the dimensions of the
operator. The concrete base should be at a distance of approximately 20 mm
from the face of the gate leaf.
SIDE VIEW
CONCRETE BASE
250 mm
300 mm
150