66
Cont
For the Quietside models listed above where the bottom of the vent termination
and combustion air intake is installed at a height of 4ft ABOVE the grade level
the following requirements must be satisfied
1. If there is not one presently installed, on each floor level where there is a
bedroom(s), a Carbon Monoxide detector and alarm shall be installed in
the living area outside the bedroom(s). The Carbon Monoxide detector
shall comply with NFPA 720 (2005 Edition)
2. A Carbon Monoxide detector shall be installed in the room where the
ODW unit is installed, the detector shall be :
a) Powered from the same power circuit that provides power for the ODW
unit. A single electrical service switch shall be used to service both the
unit and the detector
b) Have battery back up power
c) Meet ANSI/UL std 2034 and comply with NFPA 720 (2005 Edition)
d) Approved and listed by a NRTL recognized under 527 CMR
3. A Quietside approved vent termination must be used. Installation of the
vent termination must be in strict compliance with Quietside’s written
instructions, and a copy of these instructions must remain with the unit
after the installation is completed.
Vent Termination requirements
As the DPW unit is a condensing product
The Vent for all Quietside DPW units shall not terminate
Over Public Walkways; or
Near soffit vents or crawl space vents or other area where condensate or vapor
could create a nuisance or hazard or cause property damage; or
Where condensate or vapor could cause damage or could be detrimental to the
operation of regulators, relief valves, or other equipment