EasyManuals Logo

RBI FUTERA XLF Series User Manual

RBI FUTERA XLF Series
128 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #17 background imageLoading...
Page #17 background image
SETUP & OPERATON HeatNet Control V3
Page 17
Non-Condensing Boilers chart can help illustrate how the
MOD-MAX value can affect the efficiency by limiting the
input until all boilers have fired. Non-condensing boiler
efficiency is relatively flat compared with condensing as
illustrated in the Typical Efficiency of Condensing Boiler
graph.
Figure 7 Typical Efficiency of Non-Condensing Boilers
Figure 8 Typical efficiency of condensing boilers
(GAMA BTS2000 method)
In the Mixed Boiler System table line 2 example, (2)
MB/MW 500s are set as Priority 1 and MB/MW 1250s set
as Priority 2. With a MOD MAX of 60%, each 500 can run
to 300M (600M total) before a 1250 is called ON (Add
Delay timer). Once both 500s are running and the 1250 is
called on, all (3) boilers will drop to a total of the 600M
BTUs: The sum of the 500, 500, and 1250 would equal
about 27% modulation: (.27 * 500M) + (.27 * 500M) + (.27
* 1.25MM) or: 135M +135M + 337M = 607M and operate
at higher combustion efficiencies (noncondensing boilers
have minimal effect individually, but can have an effect if
many are used).
If CB/CW Fusion boilers are substituted for the MB/MW
Futera III boilers, the efficiency is greatly increased due to
the condensing mode of these boilers. When using CB/CW
Fusion boilers, during the first 2850 MBTH of load, the
combustion efficiency is maximized by running the CB/CW
Fusion boilers from low to middle input rates. See: Typical
Efficiency of Condensing Boiler graph.
Figure 9 Boiler System Response 1
(2) MB/MW 500s, (3) MB/MW 1250s
When running non condensing boilers at low
input rates, the risk of condensing should be
considered.
The Boiler System Response 1 chart illustrates how each
boiler (in the example) is brought on and fires to 60%, drops
to a lower fire rate and then adds the next boiler (vertical
dashed lines). Once all boilers are firing, the modulation is
released allowing all boilers to fire to 100%.
Now, if (1) MB/MW 500 (one of the MB/MW 500s was
brought offline) were used with (3) MB/MW 1250s and the
Mod-Max is set to 60%, the MB/MW 500 would fire to 300
MBTUs and wait for the MB/MW 1250 (Boiler System
Response 2 graph). Now, the minimum input rate would be
312M (MB/MW 1250) + the 125M (MB/MW 500) (already
running, but dropped to low fire when the MB/MW 1250
fired), the total being 437M. With a 60% MOD-MAX
clamp, there would be 137 MBTUS more than needed and
added to the system when the MB/MW 1250 fired.
The PID algorithm would then compensate for the
discontinuity (bump) in BTUs and the MB/MW 1250 could
shut off (short cycle).
This discontinuity is observed in the graph below, (Boiler
System Response 2) where the jump from the MB/MW 500
@60% to the firing of the MB/MW 1250 is apparent.
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
1.00
0 1,000,000 2,000,000 3,000,000 4,000,000 5,000,000
Input, %
System Load, Btu/Hr
Blr 1+2+3 (2250 MBTU)
Blr 1+2+3+4 (3500 MBTU)
Blr 1+2+3+4+5 (4750 MBTU)

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the RBI FUTERA XLF Series and is the answer not in the manual?

RBI FUTERA XLF Series Specifications

General IconGeneral
BrandRBI
ModelFUTERA XLF Series
CategoryController
LanguageEnglish

Related product manuals