08.02.2012 Retsch GmbH 16 0002
Preparation of the pressing process
Place the tool slide into the filling or cleaning position.
Place the press ring into the die of the press tool.
Fill in the sample material by means of the filling funnel.
Pay attention that no material is laying on the ring rim.
Remains on the ring rim can be removed by means of a
brush.
Put aside the filling funnel and push the tool slide into
the pressing position slowly and steadily. The slide locks
into place.
You can then close the hood and start the PP40.
Please take necessary measures, depending on the
dangerous nature of your pressing material, to avoid danger
to persons.
Pellet press ring filling level
If the filling level of the pellet press ring is too high or too low
the pressing result will be impaired.
Please take such measures in accordance with the
hazardousness of your sample material as to avoid any
possible danger for persons coming into contact with it.
Parameter Setting Example
Sample: cement clinker
Pellet press ring filling level
net weight:
ring 51,5 / 35 x 8,6 approximately 12g
ring 40 / 32 x 14 approximately 14g
force progression:
pressing force
ca. 12 t
build-up time
20 s
holding time
20 s
release time
20 s
The values of this example are an example and may vary
depending on cement clinker and pressing tools .
Removal of the pellet
To remove the pellet, the sliding tray is pulled into the
position for cleaning and snaps in audibly. The display shows
“Cleaning”.

Table of Contents

Related product manuals