4.4.4. Connecting the Grid and Backup Loads
Prerequisite
Select cables according to the below specification. You can amplify appropriate diameter selection of the
alternating current (AC) cable for the long grid-connection distance.
Specification
Range
Recommended value
Conductor cross-sectional area of cables (mm²)
2.5 – 6.0
4.0
External diameter (mm)
8 14
14
Additional grounding cable cross-sectional area (mm²): 4
Procedure
1. Open the cable gland, insert cables through the hole, and connect the cables to the L1, L2, L3, PE, and
N terminals.
ATTENTION: (Australia only) Do NOT connect the PE terminal of the BACK-UP port.
ATTENTION: If the grid cables are not connected correctly, an error “Master Grid Phase Error” will occur.
For details, refer to Chapter 7 “Troubleshooting”. If this error occurs, switch the position of L2 and L3
cables.
2. Connect the cables to the BACK-UP and GRID ports on the inverter.
Insert the cables and tighten the locknut in each cable.
Install the protective covers to the cable connectors.
Tighten two screws to secure each connector tightly.