22
1.
Prepare the following tools.
Tools Crimping pliers
Connection sleeve
(mm)
Insulation tape
Contraction tube
(mm)
Spec MH-14 20xØ6.5(HxOD) Width 19mm 70xØ8.0(LxOD)
Shape
2.
As shown in the gure, peel o the shields from the rubber and wire of the power
cable.
- Peel o 20 mm of cable shields from the pre-installed tube.
• For information about the power cable specications for indoor and
outdoor units, refer to the installation manual.
• After peeling o cable wires from the pre-installed tube, insert a
contraction tube.
CAUTION
(Unit: mm)
120
60
202020
180
Power cable
20
Pre-installed tube for the power cable
3.
Method 1
Push the core wire into the sleeve from both sides.
Connection sleeve
Method 2
Twist the wire cores together and push it into the sleeve.
Connection sleeve
4.
Using a crimping tool, compress the two points and ip it over and compress another two points in the same location.
- The compression dimension should be 8.0.
- After compressing it, pull both sides of the wire to make sure it is rmly pressed.
Compression
dimension
Method 1
Compress it 4 times.
5 mm
Method 2
Compress it 4 times.
5 mm
How to connect your extended power cables
Wiring Work (Continued)