14 S&C Instruction Sheet 761-505
Installation
Installing Vertical Operating Pipe
STEP 11. One of the pipe sections furnished is threaded at
one end to accommodate the operating handle
assembly. See Figure 13. Install this section of
pipe last, with the threads at the lower end.
If only one vertical operating-pipe section is
required, proceed to Step 14 on page 16.
Figure 13. Threaded vertical operating pipe.

Other manuals for S&C Alduti-Rupter

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the S&C Alduti-Rupter and is the answer not in the manual?

S&C Alduti-Rupter Specifications

General IconGeneral
BrandS&C
ModelAlduti-Rupter
CategorySwitch
LanguageEnglish

Related product manuals