SITRANS P300 (7MF8.23.. 7MF8.24.. 7MF8.25..)
20 A5E03434759-01, 08/2011
Commissioning for gases
Usual arrangement Special arrangement
Measuring gases above the pressure tapping point Measuring gases below the pressure tapping point
①
Pressure transmitter
⑤
Pressure line
②
Shut-off module
⑥
Shut-off valve
③
Shut-off valve to process
⑦
Shut-off valve (optional)
⑧
Condensate vessel (optional)
④
Shut-off valve for test connection or for bleed
screw
⑨
Drain valve
Condition
All valves are closed.
Procedure
To commission the transmitter for gases, proceed as follows:
1. Open the shut-off valve for the test connection
④.
2. Via the test connection of the shut-off fitting
②, apply the pressure corresponding to the start of scale value to the
pressure transmitter
①.
3. Check the start of scale value.
4. If the start of scale value differs from the value desired, correct it.
5. Close the shut-off valve for the test connection
④.