EasyManua.ls Logo

Siemens SGIM-3258C

Siemens SGIM-3258C
52 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Figure 21. Connection of Bus at Shipping Split
Electrical Connections
28
A: Shipping split, as shipped. Insulation boots are factory
installed in correct location. Bus bars and hardware are
mounted on a temporary shipping bracket in the one of the
units to be connected. (Bus bars and hardware may be
packed separately in unusual situations).
B: Shipping split assembly in progress. Insulation boots have
been removed, and bus bars have been installed. Connection
bolts have been correctly torqued. Unit is ready for reinstalla-
tion of insulation boots.
C: Insulation boots have been reinstalled. Unit is ready for
reinstallation of main bus compartment barrier (designated R
in Figure 25).
D: Taped bus joint configuration, used for joints where a boot
is not available. This illustrates a taped connection for multiple
cable terminals. After cables have been installed, the cable
terminations and the exposed bus must be insulated.
03367-89 03365-89
03364-89
01743-95
Courtesy of NationalSwitchgear.com

Table of Contents

Related product manuals