Commissioning
4.2 Commissioning with the IOP
SINAMICS G120D converter
66 Getting Started, 07/2016, FW V4.7 SP6, A5E38556189B AA
Set the Ramp Down time in seconds.
This is the time the Inverter/motor system will take from
being given the OFF1 command, for the motor to reach
a standstill.
A summary of all the settings is display.
If the settings are correct, select Continue.
two options:
Save settings
Cancel Wizard
If save is selected, a factory reset will be performed then
the settings are saved to the Inverter memory. The loc
a-
tion of safe data is assigned using the "Parameter sa
v-
ing mode" function in "Parameter settings" in
"Menu".
The basic commissioning of your converter is finished.