Commissioning
How to procede
²
Commissioning and installation have to be executed according to the user manual.
²
During installation of a device, the generator, its accessories and the secondary devices – like the protec-
tion relays – must be disconnected and properly grounded.
²
During the insulation tests for the generator or the excitation system according to IEC60034-1/IEEE421.3
the device has to be disconnected.
A.2
Commissioning and Maintenance
A.2 Commissioning
SIPROTEC, Coupling Units for Generator Protection, Manual 63