24
A90-4T045B
A90-4T060
245
210/200
425
410
390
188
137
7.5
A90-4T075
A90-4T090
300
266
491
473
450
206
168
9
A90-4T110
A90-4T150
335
286
491
471
450
206
170
9
A90-4T176
335
286
623
601
570
293
248
11
A90-4T210
A90-4T253
400
330
743
723
690
300
246
13
A90-4T304
2.3 Installation Site Requirements and Management
Attention
1.
When carrying the inverter, hold its bottom.
If you hold the panel only, the body main fall to hit your feet.
2.
Install the inverter on non-flammable boards (e.g. metal).
If the inverter is installed on a flammable object, a fire may occur.
3.
When two or more inverters are installed in one control cabinet, please install a
cooling fan and keep the air temperature below 50 at the air inlet.
Overheating may cause fire and other accidents.
2.3.1
Installation site
The installation site should meet the following conditions:
1.
The room is well ventilated.
2.
The ambient temperature is -10°C to 50°C.
3.
The controller should be free from high temperature and humidity (less than
90%RH) or rainwater and other liquid droplets.
4.
Please install the inverter on a fire-retardant object (e.g. metal). Never install it
on flammable objects (e.g. wood).

Table of Contents

Related product manuals