PRE-OPERATION INSPECTION
GTZZ15J Operation Manual 5-7 © Nov. 2022
Inspect maintenance-free batteries
Wear protective gloves properly.
Ensure that the connections of battery cable have
not been corroded.
Ensure that the battery is installed reliably and the
cable is connected tightly.
Connect the battery charger cables to the correct
terminals on the battery (the red cable to the
positive, and the black cable to the negative).
Connect the charging plug to a 220V socket.
Result: The battery could be charged normally, and
the charge indicator is lit.