Paint only when the fire is OFF and cold. Always mask off the surrounding area to prevent contamination
with overspray.
Ventilate the room during the use of the spray. DO NOT attempt to spray paint the coals or ceramics, or
wash them in water.
Advise that the fire will emit a “newness” smell for a time after initial commissioning and that extra
ventilation may be needed during this time.
Advise that the fire is fitted with a spillage safety device (O.D.S.). If the fire shuts down, this system may
be in operation.
If spillage is suspected, SWITCH APPLIANCE OFF and call in the installer to investigate any problems.
SECTION 15: SERVICING
Isolate the fire from the gas supply.
Ensure that the fire is fully cold before attempting service.
A suggested procedure for servicing is detailed below:
1. Lay out the dust sheet and tools required.
2. Remove the cast front fret.
3. Remove the glass panel.
4. Carefully remove the ceramic components
5. Remove the two screws at the base and back that retains the tray in place and disconnect from the
isolation tap.
6. Remove the burner tray and other components as required taken extra care with the slide control
mechanism and battery holder where applicable.
7. Disconnect the gas supply, to the appliance and disconnect the isolation tap
8. Remove convector box by, firstly protecting the hearth from potential damage, unroll the coiled
tensioner cables from the rear of the firebox, remove the securing nipples and tensioner adjusters,
the firebox is now released from the opening and can be slid outward onto the hearth.
9. Check the fireplace opening for rubble accumulation and remove, if debris is excessive, initiate
remedial work on the flue.
10. Check the flue with smoke pellet for correct operation.
11. Refit convector box using new seals where necessary
12. Strip off the burner pipes and clean thoroughly.
13. Clean out the injector, pilot assembly and burner tube. DO NOT remove the pilot injector.
14. Re-assemble and re-fit the burner tray.
15. Turn on the gas supply, and leak test.
16. Refit the decorative casting and ceramics.
17. Check any purpose provided ventilation is un-obstructed.
18. Light the fire and test for spillage.
19. Check setting pressure and safe operation of the appliance.