9 Operation
SMA Solar Technology AG
Operating manualSTP15-25TL-30-BE-en-1754
Requirements:
An SD memory card with a maximum memory capacity of 2GB is required.
The SD memory card must be formatted as FAT32.
An "Update" directory must be created on the SD memory card.
The update file must be available and saved in the "Update" directory to the SD memory card.
Procedure:
1.
DANGER
Danger to life due to electric shock
Disconnect the inverter from all voltage sources and open the lower enclosure lid (see
Section11, page76).
2. Loosen the screw of the communication assembly and slightly flip up the communication
assembly.
3. Insert the SD memory card into the slot with the slanted corner facing downward until it locks
into place.
4. Fold the communication assembly downwards and tighten the screw.
5. Commission the inverter (see Section7.3, page42).
The firmware is being updated during commissioning. As soon as the "Update completed"
message is displayed, the firmware update is completed. The message is displayed for
30seconds. Afterwards, the inverter displays its initialization messages.
6. If the firmware update failed, repeat the process.
7. Check the firmware version. To do this, access the user interface of the communication product
or SunnyPortal.
8. If the updated has been successfully updated, remove the SD memory card from the inverter.
To do this, proceed as follows.
9.
DANGER
Danger to life due to electric shock
Disconnect the inverter from all voltage sources and open the lower enclosure lid (see
Section11, page76).
10. Loosen the screw of the communication assembly and slightly flip up the communication
assembly.
11. Slightly press in the SD memory card and release it.
The SD memory card jumps out of the slot.
12. Remove the SD memory card.
13. Fold the communication assembly downwards and tighten the screw.
14. Commission the inverter (see Section7.3, page42).
15. If necessary, repeat inverter detection in the communication product (see the manual for the
communication product).