SMA Solar Technology AG Commissioning
Installation Guide SMC6-8TL-IEN101040 49
Undervoltage Test
After the overvoltage test, the inverter performs the
undervoltage test. During the test sequence, the current
calibration value of the voltage limit applied is shown in
the display of the inverter.
The voltage limit is increased successively until the shut-
down threshold is achieved and the inverter disconnects
from the grid.
Once the inverter has disconnected from the grid, the display successively shows the following values
one after the other:
•Disconnection value,
•Calibration value,
•Reaction time,
Present grid voltage.