5. Commissioning of inverter
5.1. Safety inspection before commissioning
Ensure that DC and AC voltages are within the acceptable range of the
inverter.
Attention
5.2. Start inverter
Step 1: Turn ON the DC switch(optional)Make sure the PV voltage 50V,
For SOFAR 1.1K~2.2KTL-G3,open-circuit voltage(Voc) of module arrays
connected in series must be 500V;For SOFAR 2.2K~3.3KTL-G3, it must be
550V.
Step 2: Turn ON the AC circuit breaker.
When the DC power generated by the solar array is adequate, the SOFAR
1.1K~3.3KTL-G3inverter will start automatically. Screen showing normal
indicates correct operation.
NOTE: Choose the correct country code. (refer to section 6.3 of this manual)
Notice: Different distribution network operators in different countries have different
requirements regarding grid connections of PV grid connected inverters.
Therefore, it's very important to make sure that you have selected the correct
country code according to requirements of local authority.Please consult qualified
electrical engineer or personnel from electrical safety authorities about this.
Shenzhen SOFARSOLAR Co., Ltd. is not responsible for any consequences
arising out of incorrect country code selection.
If the inverter indicates any fault, please refer to Section 7.1 of this manual
trouble shooting for help.