2.
Verify that SolarEdge SetApp is installed on your mobile device.
3.
Remove the cover from the Power Bank input port at the bottom of the Synergy
Manager. Connect the USB cable between the Power Bank and the input port -
Upon connection, all LEDs light steady for one minute, and then alternate blue /
green.
NOTE
Alternating red / blue LEDs indicat a poblem with the power bank.
Figure 25: Pre-commissioning the inverter
4. Start SetApp on your mobile device and follow the on-screen instructions.
5.
When instructed, hold the ON/OFF/P Switch in P position and release within two
seconds.
6. If the Synergy Manager is equipped with a DC Disconnect Switch, turn it to ON
position.
7. Continue to follow the on-screen instructions to set the inverter.
8. When instructed, disconnect the power bank and cover the power bank input port.
9. Turn-off the DC Disconnect Switch or the ON/OFF/P Switch.
10. Wait until the inverter shut off (all LEDs turn-off).
11. Turn-on the DC Disconnect Switch and ON/OFF/P Switch.
Three Phase Inverter with Synergy Technology P/N: SExxK-xxxxIxxxx SExxK-xxxxIxxxx
49 Pre-commissioning (Off-Grid)