www.stiebel-eltron.com DHM | 39
ENGLISH
INSTALLATION

11. Commissioning
11.1 Initial start-up
26�02�05�0087
Fill the appliance by running the tap several times until the
pipework and appliance are free of air.
Carry out a tightness check.
Insert the power cable plug, if present, into the standard
safety socket or set the fuse/MCB.
Check the function of the appliance.
11.2 Appliance handover
Explain the appliance function to users and familiarise them
with its operation.
Make users aware of potential dangers, especially the risk of
scalding.
Hand over these instructions.
11.3 Recommissioning
!
Material losses
Following an interruption of the water supply, recommis-
sion the appliance by carrying out the following steps,
in order to prevent irreparable damage to the bare wire
heating system.
Isolate the appliance from the power supply. Pull the power
cable plug, if present, from the socket, or remove the fuse/
reset the MCB.
See chapter "Initial start-up".
12. Shutting down
Isolate the appliance from the power supply by means of the
fuse/MCB in your fuse box or by pulling the power cable plug
from the socket.
Drain the appliance (see chapter "Maintenance").