Ver11 20220802
1 add requirement to cable fixture
2 add operation in internal devices
3 reorganize chapters structures from flat to pyramid.
Ver12 20240110
1 Updated transformer-related drawings
2 Added information related to cold start
3 Added the below notices:
• It is recommended to use tin plated aluminum
terminals or tin plated copper terminals.
• Do not operate the load switch when the transformer
is under load.
• Remove the cover on the pressure relief valve
• Cable clips are provided for the standard equipment
• Reserve sufficient length in HV cables
4 Add cable clamp fixing diagram and related description
5 Add transformer loss information
6 Modified torque requirements
7 Added information about how to deal with oil leakage
8 Added web address