BHT-412-MM-2
5-00-00
Export Classification C, ECCN EAR99
The following inspection is not required if planetary
spider 412-040-785-103 is installed.
9. Perform magnetic particle inspection on lower planetary
spider 204-040-785-003.
USE OF ANY FORM OF LUBRICANT TO
FACILITATE INSTALLATION OF GEAR ON SHAFT
WILL RESULT IN TORQUE LOSS OF
ATTACHMENT BOLTS AND SUBSEQUENT
FRETTING DAMAGE.
During assembly of spiral bevel gear to shaft, ensure
mating surfaces are dry.
BHT-412-CR&O 10. Assemble transmission.
5-33. EACH 3000 HOURS OF TRANSMISSION (412-040-002) OPERATION (CONT)
DATA REFERENCE INSPECTION TASK DESCRIPTION
INITIAL
MECH OTHER
26 FEB 2013 Rev. 16 Page 175/176