ENGLISH
V4-007 J EN
Originalbetriebsanleitung
32
8.10
Intake lter
Before replacing the lter element, take the compressor unit out of operation
and prevent it from being started up inadvertently.
Please observe the instructions of the unit manufacturer too!
Check degree of lter soiling and replace lter cartridge if necessary, •
max. -45 mbar
Replace lter cartridge•
Starting strainer
In case of intake from a closed piping system, a starting strainer or a lter housing •
is to be installed upstream of the machine‘s intake side. Depending on design /
order, this is included in the scope of supply.
This protects the machine against contamination and from foreign particles that •
are carried into the intake ow.
The resistance of the starting strainer / lter element is to be monitored.•
The maximum resistance of - 45 mbar must not be exceeded.•
If the strainer remains clean after approximately 500 operating hours, it can be •
dismantled and replaced by the supplied adjusting ring.
The lter element is to be checked or replaced according to the respective speci-•
cations of the ‘intake lter’ in the maintenance plan.
The starting strainer consists of ne-meshed gauze with mash size of 0.5 mm with •
a perforated sheet according to DIN 24041 R 6.3-8.
DN Øf m g
--------------------------------------------------------------------------------------------------------------------
125 180 250 15
150 212 265 15
200 268 280 15
250 325 220 15
300 375 200 15
350 435 460 15
400 485 342 15