6
2. Delivery Check On
Arrival/Off-Loading and
Movement To The Site
2.4 Forklift Trucks
The forks must only be applied under the
unit base frame and not against the unit
base frame. The lift point should be as
near as possible to the centre of gravity
(see Figures 4 and 4a). In the case of
larger units the use of several forklift
trucks may be required.
2.4.1. Roller Movement
Units fitted with base frames may be
moved on roller trolleys or tubular rollers
(see Figure 5).
Figure 4
Figure 4A
Figure 5