Installation: Mechanical
Storage
If the chiller is to be stored for at least one month prior to installation, observe the fol-
lowing precautions:
the pressure of dry nitrogen in the refrigerant circuit. If the pressure is below 5 psig (34
kPa) at 70°F (20°C), call a qualified service organization and the appropriate Trane sales
office.
Location Requirements Noise Considerations
Note: Consult an acoustical engineer for critical applications.
Foundation
Provide rigid, non-warping mounting pads or a concrete foundation of sufficient
strength and mass to support the chiller operating weight (including completed piping
and full operating charges of refrigerant,
oil and water).
After the chiller is in place, level the chiller within 1/4" (6 mm) over its length and
width. Trane is not responsible for equipment problems resulting from an improperly
designed or constructed foundation.
Vibration Eliminators
that could introduce vibration into occupied spaces.
Note: Do not use metal braidedtype eliminators on the water piping. Metal braided
eliminators are not effective at the frequencies at which the unit
CVGF-SVX03B-EN
46