3. Installation instructions
3.1. Preparations before installation
- Prepare the needed tools and equipment:
o Appropriate lifting equipment
o Anti-abrasion hydraulic oil
o Rotary hammer drill
o Chalk and tape measure, magnetic plumb
o Sockets and open wrenches, a set of inside hex wrenches,
screwdrivers
o Hammer, sharp nose pliers
o Socket spanners Ø 17, 19 and 22
- Check that all parts are in the packages (refer to Annex1 packing list)
- Check the ground conditions of the installation site
o The lift should be fixed on a smooth and solid concrete ground with
its strength more than 3000PSI (2.1kg/mm³), tolerance of flatness
less than 5mm and minimum thickness of 200mm. In addition,
newly built concrete ground must undergo more than 28 days of
cure and reinforcement!
3.2. Precautions for installation
- Make sure that the two posts are paralleled and vertical to the ground
- The joints of the oil hose and steel cable must be firmly connected in order
to avoid the looseness of the steel cable and leakages of the hydraulic
system
- All bolts should be firmly screwed tight
- DO NOT PLACE ANY VEHICLE ON THE LIFT DURING TRIAL RUNS!