6.2.3.2. Mechanical handling of loads
Only statutory mechanical lifting devices,
appropriate for the operation are allowed for
use.
Check the condition of the lifting gear such as
slings or cables before each use and report any
defects.
Place lifting accessories and step back to a secure
distance from the load and other materials which
could get affected.
Comply with all instructions given by the team
chef who is specifically trained for this.
Cause no sudden acceleration or deceleration of
the moving load.
When conducting difficult or dangerous lifting
operations, or in the case that the crane operator
has no obstruction free visual control of the
entire trajectory of the load, the crane operations
are directed by a banksman who is in constant
communication with the crane operator by
means of a previously agreed sign code.
If necessary, use tag lines to control the load
from distance. Keep hands clear of suspended
load if hands could get caught between the load
and another object. Swinging and/or unforeseen
movements with the load can cause serious
accidents.
6.2.4. Storage
StorageStorage
Storage
Proper storage of the parts is fundamental to
keep them in good working condition.
Wherever possible, store the material in a place
protected from atmospheric impact to avoid
wear.
It is recommended to place parts of the same
type and dimensions in its respective container
(boxes, steel pallets, etc.).
Ensure the stability of any piles, bearing in mind
the following aspects:
- Load-bearing capacity of the ground
- Varying ground levels
- Levelling of the packages
- Package or container support
- Package stability
- State of the strap
- State and capacity of the containers used
- Do not stack full containers on top of empty
or half-empty containers
- External conditions (wind, risk of another
object hitting the pile, etc.)
6.3.
6.3.6.3.
6.3.
INSPECTION AND MAINTENANCE
INSPECTION AND MAINTENANCEINSPECTION AND MAINTENANCE
INSPECTION AND MAINTENANCE
6.3.1. General guidelines
General guidelinesGeneral guidelines
General guidelines
ULMA is responsible for the delivery of the
products, for sale or rent, in good working
condition.
From the moment of delivery, the responsibility
for correct use, inspection and product
maintenance passes on to the purchaser or
lessee. All damaged and broken parts, parts with
missing components, i.e. all parts in no proper
working condition must be removed from
service.
For use, inspection and maintenance of the
product, special attention should be paid to the
following points:
- Items aimed to ensure people´s safety
- Items made of aluminium, as they are more
vulnerable to damages of the welded joints
and deformation