EasyManuals Logo

UNI EV Series User Manual

Default Icon
21 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #8 background imageLoading...
Page #8 background image
Operating and mounting manual (translation)
EV / EVF
_______________________________________________________________________________________________________
220.100.091-05 Page 8 /21 Version: 06/2017
TM 4474
6.1 Commissioning
Before commissioning, check the data on material, pressure, temperature and flow direction
with the layout plan of the pipework system.
Depending on the field of application, the local regulations have to be observed, e.g. the
operation safety order.
Residues in the pipework and the valve (dirt, weld beads, etc.) will inevitably result in leaks.
Leakage inspection of the installed valve.
6.2 Shutting down
Depending on the field of application, the local regulations have to be observed, e.g. the
operation safety order.
6.3 Maintenance
Solenoid valves have to be checked at regular intervals for proper function and internal leak tightness.
The intervals for regular inspections have to be defined by the operator according to the operating
conditions. UNI-Geräte recommends an internal visual inspection once a year and an overhaul of the
valve after 2 years or after the following number of switching cycles at the latest:
Application
temperature
DN 25 DN 80 DN 150 > DN 150
25°C
150 000 75 000 25 000 20 000
> 25°C
50 000 25 000 25 000 5 000
6.4 Putting back into operation
When putting a valve back into operation, ensure that all the necessary steps described in section 5.2
(Installation) and section 6.1 (Commissioning) are repeated.
7.0 Troubleshooting
7.1 Detection of defects
DANGER!
Be sure to observe the safety instructions during troubleshooting.
If the malfunctions cannot be remedied using the following “Troubleshooting plan (7.2)” please
contact the manufacturer.
In the event of faults in the function or operating behaviour of the valve, check whether the installation
work was carried out and completed as described in this operating manual.
Depending on the field of application, the operation safety order must be observed.
Check the data on material, pressure, temperature, voltage and flow direction with the layout plan of
the pipework system. In addition, check whether the operating conditions correspond to the technical
data in the data sheet or on the rating plate.
7.2 Troubleshooting plan
Malfunction Possible causes Remedy
No flow Valve does not open Switch on solenoid drive (800)
Check operating voltage
Working pressure too high Compare working pressure with the data
on the rating plate
Flange covers were not removed Remove flange covers
Low flow rate Clogging in the pipework system Check pipework system
Valve leaking at seat,
no internal tightness
Valve seat gasket (400) or valve seat
(100) damaged by external particles
See section 8 or replace valve
No external tightness Gaskets damaged See section 8 or replace valve

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the UNI EV Series and is the answer not in the manual?

UNI EV Series Specifications

General IconGeneral
BrandUNI
ModelEV Series
CategoryControl Unit
LanguageEnglish