APPENDICES
Appendix A: Checklist for Completed Installation
Before initial start-up of the VRC, print this checklist and mark each item as it is confirmed "completed."
Mechanical Checks
Completed Item
There is sufficient clearance for unit access and maintenance.
All fasteners and fittings are firmlysecured.
Unit is oriented correctly in the rack cabinet: cool, supply air is at the front and hot, return air is at the back.
Foreign materials are removed from the area (shipping material, packaging, tools, etc.)
Condensate-drain piping is properly connected.
Electrical Checks
Completed Item
Power-supply voltage meets the rated voltage on the unit name plate.
Unit is plugged-in to an appropriate supply outlet.
Communication and control cables are firmly connected.
Start-up Checks
Completed Item
Confirm no alarms or warnings displayed.
Unit is operating without vibration or noise, and air is flowing.
System is operating within range of the set parameters.
35

Other manuals for Vertiv VRC100

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Vertiv VRC100 and is the answer not in the manual?

Vertiv VRC100 Specifications

General IconGeneral
BrandVertiv
ModelVRC100
CategoryFreezer
LanguageEnglish

Related product manuals